FOR IMMEDIATE RELEASE


Proposed PJM RPM reforms spark detailed debate

Rockville, MD (January 23, 2015) -- FERC was inundated with comments Tuesday on PJM's proposed capacity performance rule changes that saw a major redesign of the reliability pricing model (RPM). Many generators supported the rules in principal after last year's polar vortex exposed the RPM as flawed, but most load interests opposed them as an expensive overreaction. PJM VP of Market Operations Stu Bresler explained the need for so-called penalty to Utility Markets Today, the nation's leading journal chronicling ongoing efforts to open competitive wholesale and retail energy markets. Utility Markets Today publisher Modern Markets Intelligence, Inc. is sharing the story here, free of charge.

The Transition Coalition – made up of the Delaware PSC, PJM Industrial Customer Coalition, retailers and others – urged FERC to reject the RTO's proposal to start the capacity performance market in 2016/2017 and 2017/2018. The base auctions for those years have already been run, so the coalition argued the extra capacity performance payments would just be a wealth transfer to consumers without any real benefits.

The coalition estimated some 96 GWs of nuclear, coal, duel-fuel units on interstate pipelines and gas units with firm supplies would clear in the 2016/2017 year at a cost of up to $2.8 billion. But those generators are already there and would meet capacity performance's higher performance rules anyways.

The results would be similar for 2017/2018 with the Transition Coalition estimating up to 110 GWs would be available at a cost of $3.6 billion.

Since generators will not perform any better with the extra money those two years, the Transition Coalition said it "was left to wonder" whether the real purpose of the proposal was to deal with generator claims of revenue shortfalls.

"We respectfully submit that resources that have cleared in prior auctions must live with the capacity supply obligations to which they have agreed," the coalition said.

PJM has cheaper options to shore up reliability for those two years, it added, such as a special procurement for dual-fuel capability given that over 20,000 MWs of gas-fired units cannot burn oil now. For 2016/2017, some 13,082 MWs (including nuclear plants) did not clear but it could still be available, it added.

Exelon owns some of those plants that did not clear in the last auction, but it views the capacity performance rules as a necessary step given the weaknesses in the RPM that the polar vortex revealed. The RPM rules do not have a meaningful penalty for generators that go out of service, which in effect ends up favoring generators that do not do enough to maintain their units by helping them keep their bids low.

The proposal is needed to make sure generators are available whenever they are needed, and at the same time, it will appropriately compensate suppliers that already exhibit high performance, said Exelon.

The generator supports the transition-year mechanisms and lauded PJM for using a market approach. The extra money will mean real improvements from some units, Exelon said.

Generators will invest more to weatherize their units, a lack of which was the main cause of outages during the polar vortex, it added. The earlier payments could also lead to gas generators getting contracts for firmer fuel.

But the transition coalition was not the only one to raise the issue of the transition years, including American Municipal Power (AMP), Old Dominion Electric Co-op (ODEC) and Southern Maryland Electric Co-op (SMECO). Those firms believe generators already have an obligation to perform from the base auctions they cleared in for 2016/2017 and 2017/2018.

PJM wanted to get the ball rolling on its capacity performance rules before the normal three-year cycle of the RPM because it is important to ensure that the needed investments are made on time, Bresler told Utility Markets Today.

"We think it's unreasonable to think that we can just – for lack of a better term and I hope you'll pardon the pun – flip a switch and all of a sudden expect increased performance in 2018 without some sort of ramp-up to get to that point," he added. "We think the transition is important, so that we begin committing at least some level of resources in the 16/17-17/18 delivery years."

That way "we can ramp up to that 80% level in 18/19-19/20 and then 100% in 2021 and beyond," Bresler said.

The reason PJM is not making all resources meet the new requirements until 2021 is to keep the cost increases from going too high, he added.

Penalty questioned

The most serious flaw in PJM's proposal, Exelon said, is the penalty structure with fines based on net cost of new entry (CONE) divided by 30 hours – based on the assumption that there could be as many as 30 performance-assessment hours each year. But there never has been as they peaked at 23 in 2013/2014 that covered the polar vortex and some heat waves in the summer of 2013, it added.

Back-casting the RTO's penalties means no generators, even those who did not respond in any of the performance assessment hours during the polar vortex, would have been fined their entire capacity revenue. No generator over the past seven years in any zone ever would have paid such a high fine – let alone the 1.5 times net CONE maximum, Exelon said.

FERC should require PJM to stiffen the rules so generators cannot benefit from the gaming the system, claiming to make investments they never do, it added.

The PJM Power Providers (P3) is concerned about the 30-hours number, suggesting PJM should have to show more reasoning on why it picked that figure. The only reason P3 could imagine was that the number was a little higher than 23, the historic peak for performance hours.

Bresler takes on 'penalty'

PJM views the calculations of the "penalty" as another instance of its balancing act, said Bresler. The penalties work out to around $4,000/MWH while the maximum price in PJM is around $2,700/MWH so they are a significant deterrent.

Bresler does not like the term "penalty," beyond its use as a shorthand, because the rules are taking back money already paid to plants and then redistributing it to better-performing generators, he noted.

"The risk of not performing and being subject to a penalty of $4,000/MWH is, in our minds, sufficient to drive that necessary investment," Bresler said. "In other words, that is not a risk a developer can take on say, willy-nilly – 'I'm going to roll the dice and hopefully the conditions won't materialize.'"

While some might feel 30 hours is too much time to spread risk around, the current penalty system is based on 500 peak hours and then no charge is issued if a unit's outages come in below its forced outage rate, he added.

Small utilities see failure

PJM failed to make its case that these major reforms are needed, AMP, ODEC and SMECO told FERC. "What we mean is that PJM has failed to articulate clear reasons why capacity performance should become the 'new normal' for PJM when the conditions that gave rise to it almost certainly are not," the three load servers said.

PJM has a number of other reforms under way to deal with the same issue with better testing of generators' weatherization, best practices for extreme cold, changes to commitment practices and other new rules that can deal with the winter peaking issue, they added.

DR group not pleased

The DR group, the Advanced Energy Management Alliance (AEMA), protested the policy as an unneeded replacement of current RPM products that will result in massive cost increases for consumers. AEMA would like FERC to keep some portion of the capacity in PJM the same product that the RPM has procured for years now, arguing that would save significant money.

Requiring DR to comply with the capacity performance measures means less of the resource would clear in the auctions, said AEMA.

"At a time when PJM seeks to implement changes targeted at increasing reliability by making more capacity resources available, it is counterproductive to implement changes that will reduce the ability for dependable and reliable demand resources to continue to participate in PJM's capacity market," it added.

Demand was high early this month, but the RTO's early responses to last year's polar vortex meant PJM did not come nearly as close to losing power the second time around, AEMA said. The peaks Jan 7 and 8 this year were among the top 10 winter peaks of all time, but the grid was fine, it added.

AEMA argued PJM should go after the main cause of the near miss in 2014 – lack of generator performance – by ramping up the penalties generators get for failing to respond when needed.

This story was originally published in Utility Markets Today (http://ow.ly/HQKa1) on January 22, 2015 and has been slightly edited for this format. To read more articles like this one, sign up for a Free Trial to Utility Markets Today.

ABOUT UTILITY MARKETS TODAY

UTILITY MARKETS TODAY is published 245 times per year on business days by Modern Markets Intelligence, Inc. UMT's mission is to deliver exclusive news chronicling ongoing efforts to open competitive wholesale and retail energy markets with in-depth analysis on why some fail and others succeed.

CONTACTS

James Downing
Editor, Utility Markets Today
Modern Markets Intelligence, Inc.
888-678-5540
james@mminews.com

Season Crawford
VP of Marketing
Modern Markets Intelligence, Inc.
888-678-4480
season@mminews.com

 

Code of Ethics

At MMI, we believe that our success and growth depends on maintaining the highest degree of ethical standards in all situations. Our industry is going through a period of rapid change, and with that comes new challenges, opportunities and ethical questions. Our Code of Ethics should serve as a guide for employees and managers dealing with ethical dilemmas. More

Core Values

To achieve our corporate mission, we have developed these governing principles: Integrity -- our role as a partner for success with each of our customers depends on honesty and ethical integrity in every word we write, every document we produce, every conference we produce and every decision we make along the way. More